China Highway metal corrugated pipe φ55/70mm precast beam galvanized corrugated pipe - China Supplier
China Highway metal corrugated pipe φ55/70mm precast beam galvanized corrugated pipe - China Supplier China Highway metal corrugated pipe φ55/70mm precast beam galvanized corrugated pipe - China Supplier China Highway metal corrugated pipe φ55/70mm precast beam galvanized corrugated pipe - China Supplier

Highway metal corrugated pipe φ55/70mm precast beam galvanized corrugated pipe

Price:元3.5 /米
Industry Category: Construction-Real-Estate
Product Category:
Brand: 衡水长江预应力
Spec: 55


Contact Info
  • Add:河北衡水北方工业基地园区东路269号, Zip: 053000
  • Contact: 高晴
  • Tel:15297607517
  • Email:1518498187@qq.com

Other Products

Description
Additional Information

Highway Metal Corrugated Pipe φ55/70mm Precast Beam Galvanized Corrugated Pipe

Construction Guide for Prestressed Galvanized Corrugated Pipe

Prestressed galvanized corrugated pipes are widely used in post-tensioned prestressed concrete projects as protective sleeves for prestressing tendons (strands, wires, etc.). Their construction quality directly affects the safety and durability of the prestressed structure. Below is a detailed construction process and key considerations.

1. Pre-Construction Preparation

1.1 Material Inspection

  • Corrugated Pipe Quality: Check for uniform zinc coating without damageHighway Metal Corrugated Pipe φ55/70mm Precast Beam Galvanized Corrugated Pipe, and ensure the pipe body is free from flattening or deformation.
  • Sealing Performance: Ensure all joint accessories (e.g., connecting sleeves, waterproof tape) are complete to prevent grout leakage.
  • Specification Matching: The diameter of the corrugated pipe should meet design requirements, typically 5~10mm larger than the prestressing tendon diameter.

1.2 Tool Preparation

  • Cutting machine (dedicated corrugated pipe cutting tool, Highway Metal Corrugated Pipe φ55/70mm Precast Beam Galvanized Corrugated Pipe to avoid burrs)
  • Waterproof tape/heat-shrink sleeves (for joint sealing)
  • Tying wires/rebar supports (to secure the corrugated pipe position)
  • Positioning and measuring instruments (to ensure accurate coordinates)

2. Corrugated Pipe Installation

2.1 Positioning and Fixing

  • Positioning According to Design Coordinates: Use rebar supports or dedicated positioning bars to secure the corrugated pipe, with spacing ≤1m (reduced to 0.5m in curved sections).
  • Curved Section Handling: Ensure smooth transitions and avoid sharp bends (minimum bending radius ≥30 times the pipe diameter).
  • Height Control: The centerline of the corrugated pipe must align with the designed position of the prestressing tendon, with deviation ≤5mm.

2.2 Connection and Sealing

  • Straight Pipe Connection: Use a corrugated pipe one size larger for sleeve connection, with overlap length ≥30cmHighway Metal Corrugated Pipe φ55/70mm Precast Beam Galvanized Corrugated Pipe, and wrap waterproof tape or apply heat-shrink sealing at the joint.
  • Branch Pipe Connection: Use dedicated tees or cross fittings to ensure sealing.
  • Vent Hole Setup: Reserve vent holes (Φ20mm plastic pipes) at the highest points of curves to prevent air accumulation during pouring.

2.3 Clogging Prevention Measures

  • Insert temporary lining pipes (e.g., PE pipes or rubber rods) and remove them after initial concrete setting to prevent grout leakage and clogging.
  • Check pipe patency before pouring, using high-pressure air blowers or hole cleaners if necessary.

3. Concrete Pouring Protection

  • Avoid Vibrator Contact: Do not allow vibrators to directly contact the corrugated pipe to prevent damage or displacement.
  • Leakage Inspection: Focus on monitoring joints; immediately flush the pipe with clean water if grout leakage is detected.
  • Protection During Curing: Avoid external impacts or welding operations that could damage the zinc coating.

4. Prestressing Tendon Installation

  • Installation Timing: Perform after concrete strength reaches 75% of the design value.
  • Lubrication to Reduce Friction: Apply dedicated lubricant (e.g., wax-based material) inside the corrugated pipe before installation.
  • Rust Prevention: Temporarily seal exposed ends of strands with waterproof tape after installation.

5. Common Issues and Solutions

Issue

Cause

Solution

Corrugated pipe flattened or deformed

Excessive pressure during pouring

Increase support density, control vibrator distance

Grout leakage clogging the duct

Poor joint sealing

Use double-layer tape + heat-shrink sleeves for enhanced sealing

Difficulty in prestressing tendon installation

Pipe misalignment or local blockage

Pre-clean ducts and adjust positioning

Industry Category Construction-Real-Estate
Product Category
Brand: 衡水长江预应力
Spec: 55
Stock:
Origin: China / Hebei / Hengshuishi
About Toocle.com - Partner Programme - Old Version
Copyright © Toocle.com. All Rights Reserved.
(浙)-经营性-2023-0192